Cabinet Affairs |
|
AGENDA SITING BOARD DEPARTMENT OF ENVIRONMENTAL
PROTECTION APRIL 8, 2003 ******************************************************** Item
1
Minutes
Submittal
of the November 13, 2002 Siting Board
Minutes. (See
Attachment 1, Page 1) RECOMMEND
APPROVAL ******************************************************** Item
2
Florida Power & Light/Manatee Power Plant Unit 3 Site Final
Order REQUEST:
Consideration of an Order, to be executed by the Siting Board,
adopting the Administrative Law Judge's Recommended Order recommending the
Siting Board grant full and final certification to Florida Power &
Light Company, under Section 403, Part II, F.S., for the location,
construction and operation of the Manatee Power Plant Unit 3, pursuant to
Subsections 403.509(1), and 403.511(1), F.S. COUNTY:
Manatee APPLICANT:
Florida Power & Light Company
(FPL) LOCATION: The
Manatee Unit 3 site is located on 72.8 acres within the 9,500-acre Manatee
Plant site in Manatee County, Florida. The Unit 3 site is approximately
4.5 miles east of the unincorporated town of Parrish, and approximately
2.5 miles south of the Manatee County-Hillsborough County
line. STAFF
REMARKS: On February 22, 2002, FPL filed a Site Certification Application
(SCA) with the Department pursuant to the Florida Electrical Power Plant
Siting Act, Sections 403.501 through 403.518, F.S. The SCA proposed the
construction and operation of an 1150 MW (nominal) electric power
generation facility. This facility would consist of four natural gas fired
170 MW combustion turbines, four heat recovery steam generators with duct
burners, a 470 MW steam turbine and generator, and ancillary equipment. No
alternative fuels are included in this certification. No new transmission
lines are included in this certification. An existing 4,000 acre cooling
pond will be used by Unit 3 for waste heat
disposal. The
existing Manatee Plant currently has two oil-fired steam electric
generating units. Each of these units has a nominal generating capacity of
800 megawatts. These units
are not certified pursuant to the Siting Act as the construction of these
units preceded implementation of the Act nor are they included for
purposes of this certification. On
November 13, 2002, the Siting Board adopted the Administrative Law Judges
recommendation to find the site in compliance with local land use plans
and zoning ordinances. On
February 19, 2003, the Administrative Law Judge issued a Recommended Order
recommending the Siting Board grant full and final certification to
Florida Power & Light Company. (See Attachment 2, Pages
1-85) RECOMMEND
APPROVAL
Siting
Board
Department of Environmental Protection
Agenda - April 8, 2003
2nd Substitute Page Two ******************************************************** 2nd
Substitute Item 3 Florida Power & Light/Martin
Power Plant Unit 8 Site Final Order REQUEST:
Consideration of an Order, to be executed by the Siting Board,
adopting the Administrative Law Judge's Recommended Order recommending the
Siting Board grant full and final certification to Florida Power &
Light Company, under Section 403, Part II, F.S., for the location,
construction and operation of the Martin Power Plant Unit 8, pursuant to
Subsections 403.509(1), and 403.511(1), F.S. COUNTY:
Martin APPLICANT:
Florida Power & Light Company
(FPL) LOCATION: The
Martin power plant site is located in an unincorporated area of Martin
County, Florida, approximately twenty-two miles inland from the Atlantic
coast, seven miles northwest of Indiantown, and five miles east of Lake
Okeechobee. STAFF
REMARKS: FPL's Martin Expansion Project (Unit 8) consists of two existing
170 megawatt (MW) combustion turbines, two new 170 MW combustion turbines,
four heat recovery steam generators and a single 420 MW steam turbine
operating as a 1100 MW combined cycle unit. The new units will be fired
primarily with natural gas with light oil as an alternative fuel. Unit 8 will use 44 acres of the
existing Martin site which is an approximately 11,300-acre parcel located
about seven miles northwest of Indiantown and five miles east of Lake
Okeechobee in western Martin County. Additional facilities
included in the project include a cooling tower, a short transmission line
and transformers and switching gear necessary to connect to the FPL
transmission system east of the site along the St. Lucie Canal. On March
5, 2003, the Administrative Law Judge issued a Recommended Order
recommending the Siting Board grant full and final certification to
Florida Power & Light Company, under Section 403, Part II, F.S., for
the location, construction and operation of the Martin Power Plant Unit 8,
pursuant to Subsections 403.509(1), and 403.511(1), F.S.
(See
Attachment 3, Pages 1-147) RECOMMEND
APPROVAL | ||||||||||||
|